Posted on: 01 May, 2019
Amendment: For any projects undergoing current renovation or demolition whichthat were constructed or renovated between 1950 and the institution of any applicable laws banning or restricting PCBs, the below guidelines are applied and a policy put in place for future work:
|
Posted on: 01 Feb, 2019
Amendment: All commercial and institutional spaces found to have lead-based hazards must adhere to U.S. EPA 40 CFR Part 745.227 work practice standards for conducting lead-based paint activities, as outlined in U.S. 40 CFR Part 745.227 for multi-family dwellings and in U.S. 29 CFR Part 1926.62 for general construction work. An occupant protection plan must be implemented during the work activities.
|
Posted on: 01 Feb, 2019
Amendment: To reduce hazards in projects constructed prior to any applicable laws banning or restricting asbestos, the following testing, evaluation and abatement protocols (as applicable) are is conducted for prior and during repair, renovation, demolition, or painting.
|
Posted on: 01 Feb, 2019
Amendment: An on-site investigation of the commercial space conducted by a certified risk assessor or inspector technician to determine the presence of any lead-based hazards in paint, dust and soil using the definitions in U.S. EPA 40 CFR Part 745.65 for residential dwellings or child-occupied facilities.
|
Posted on: 15 Aug, 2018
Amendment: In 29 May, 2018 AAP, remove: "the US Consumer Product Safety Commission". Add: "an agency focused on protecting the public from risk or injury associated with consumer products,”
|
Posted on: 07 Jun, 2018
Amendment: In Core & Shell Scope, remove: "Entire Building". Add: "Extent of Developer Buildout"
|
Posted on: 20 Oct, 2017
Amendment: For Part 5b, remove: "Project develops a plan to upgrade current mercury-containing lamp". Add: _“Project does not install any lamps not compliant with the low-mercury limits specified in Appendix C, Table A5. Project develops a plan to upgrade any existing non-compliant lamps to low-mercury or mercury-free lamps.”
|
Posted on: 20 Oct, 2017
Amendment: For Part 1c, add: "For door hardware, project teams must document attempt to meet the requirement and demonstrate a petition or a formal request has been filed with manufacturers who were unable to meet their needs." after "Not more than 100 ppm (by weight) added lead in all other building materials."
|
Posted on: 20 Oct, 2017
Amendment: In part description, remove: "following guidelines". Add: "below guidelines, and a policy is put in place for future work"
|
Posted on: 20 Oct, 2017
Amendment: For Part 3a, remove: "or by a U.S. EPA accredited company experienced in asbestos assessment". Add: "or" before "accredited asbestos consultant..."
|